This was reported by the president of the institution, Salvador Fuentes, following the agreements of the Emproacsa board of directors. The first action corresponds to the second phase of the new pipeline connecting the Iznájar water treatment plant with the Casilla del Monte reservoirs. This intervention is carried out in three phases of 8 kilometres each; the first is already 25% complete, and the second has now been awarded for 12.5 million euros, covering the stretch from Los Prietos to CP-205.
Fuentes highlighted that this work, with an execution period of 18 months, will act on 8,466 metres of length passing through the municipalities of Encinas Reales and Lucena. "We are putting 12.4 million into a work with an execution period of 18 months," the provincial president explained, valuing that the project, although ambitious and complex due to the motorway crossing, "is going well in time and form".
“"It is a first-rate network where there were 300 water leak incidents annually due to the condition of the pipes. This work will solve the problems, the 300 incidents per year, a loss of thousands of cubic metres of water."
The second announced work affects the Montilla-La Rambla general pipeline, with a budget of 1,527,578 euros. Fuentes indicated that a bypass is being established because the previous pipeline was in expansive clay, which caused movements and alarming leak conditions. A parallel diversion has been carried out on solid ground to fix the structure and avoid incidents.
This pipeline supplies La Rambla, Montalbán, La Victoria, Santaella, La Carlota, Guadalcázar, San Sebastián de los Ballesteros, Fuente Palmera, Almodóvar del Río and Posadas. The action is currently on the State Sector Procurement Platform for tendering. The works consist of the installation of 2,052 linear metres of ductile iron pipeline with the appropriate protection systems.