The works, carried out in coordination with the water service concessionaire Aqualia, will significantly enhance stormwater evacuation capacity at a critical point in the city's sanitation network. The fault had revealed old, decades-old, poorly maintained culvert galleries causing leaks.
During the visit, attended by government councilors Francisco Lechuga, Javier Padorno, and Carmen Elvira, as well as Aqualia's city manager, Manuel Holguín, and the technical team, the mayor observed the progress of a priority intervention addressing damage from recent torrential rains.
90 linear meters of the planned 226 meters of 1,200 mm diameter PVC pipe have already been installed and covered, representing approximately 40% of this section. The infrastructure also shows 70% progress in concrete work.
The project also includes the installation of a large prefabricated concrete manhole (2 by 2.5 meters) and a final section with 1,500 mm diameter concrete pipe, along with a new discharge chamber.
Julio Millán highlighted the importance of this action in providing a solution to the problems faced by residents in the area, by renewing and expanding the existing infrastructure to reduce the risk of future incidents.
Economic area councilor Francisco Lechuga noted that these interventions are commissioned to Aqualia and will be followed by a second phase, funded by EDIL Funds, connecting the current work to the Gran Eje.
The intervention will not be limited to renewing underground infrastructure but also includes the subsequent complete resurfacing of the avenue, coordinating sanitation and surface repair to avoid successive interventions on the same road and offer a comprehensive solution.